{"id":3392,"date":"2024-07-12T09:07:21","date_gmt":"2024-07-12T09:07:21","guid":{"rendered":"https:\/\/www.cervitech.nl\/?post_type=projecten&p=3392"},"modified":"2026-04-02T09:27:48","modified_gmt":"2026-04-02T09:27:48","slug":"relox-rto-bij-berry-global-hardeberg","status":"publish","type":"projecten","link":"https:\/\/www.cervitech.nl\/en\/projecten\/relox-rto-bij-berry-global-hardeberg\/","title":{"rendered":"Amcor Hardenberg"},"content":{"rendered":"

At Amcor (formerly Berry BPI), an old afterburner sits on the roof, which no longer meets current emission and energy requirements. In the preliminary phase, CERVITECH BV conducted a production study and combined this with future plans.<\/p>\n\n\n\n

This research was the starting point of the final project. This project not only consists of supplying the new Regenerative Thermal Oxidizer (RTO), also called an afterburner, but also of optimizing the production equipment, designing the assembly of production machines, piping, valves and the RTO and putting the entire assembly into production.<\/p>\n\n\n\n

Phase 1<\/h5>\n\n\n\n

A blueprint of the factory is created through various flow and concentration measurements on various product machines, which are linked to the old RTO. Based on these measurements, an accurate picture of the current situation is recorded.<\/p>\n\n\n\n

\"\"
The foundation on the roof is ready. <\/figcaption><\/figure>\n\n\n\n
Phase 2<\/h5>\n\n\n\n

This phase involves developing a plan to improve the process values as measured in Phase 1. In addition to making this plan, it will also be implemented. By executing, a new blueprint is created with new values for both flow and concentration.<\/p>\n\n\n\n

Phase 3<\/h5>\n\n\n\n

Determine what the capacity of the new RTO will be with the input of parameters and the values that were previously determined. In this phase, the complete project plan has been developed in terms of project matters and schedules.<\/p>\n\n\n\n

Phase 4<\/h5>\n\n\n\n

In this phase, the realization of the project plan begins, up to the actual installation of the new RTO. A new foundation is laid on the roof so that the new RTO can be placed on it. The old valve motors are replaced with fail-safe motors. Cervitech also supplied these.<\/p>\n\n\n\n

Phase 5<\/h5>\n\n\n\n

Installing and fully connecting the RTO to the foundation on the roof.<\/p>\n\n\n\n